Infrastructure Under-construction on PPP Basis – National Highway G206
ACEG Invest.  |  Updated: 2018-01-30  |  Views: 39171

The National Highway G206 Shucheng Section is with a length of 23.1KM starting from the Interchange Overpass named Shuqing in Shucheng County and ending at the boundary with County Tongcheng .

The designed speed is 80km/h for the main road with a width of 24.5m and 60km/h for the urban trunk road with a width of 32m.

The initial shareholder of this project is Tongyun Transportation Construction Investment Co., Ltd. in Shucheng County, accounting for 20% of the shares and the social capital - Anhui Construction Engineering Group Co., Ltd. accounting for 80% of the shares.

The total investment of the project is RMB 840 Million Yuan and the construction cost is RMB 688.5 Million Yuan. The total construction period is 18 months and the operation period is 10 years.

The project commenced in January 2017 and the scheduled completion date will be in July 2018.

 

尹锡悦和夫人子女| 山东舰持水量| 99久久精品久久久久久引换脸| 小男人遇上大女人| 设乐夕日个人资料| 最新m网站| 清新头像| 诗词大会第一季免费观看完整版| 4509开头的身份证是哪里的| 本院属亚代达罗斯民多弓人么弄 | scle| 咸阳市| 知敬畏,存戒惧,守底线心得体会 | 伍六七之记忆碎片| 五花大绑捆绑游戏| 英语选择性必修三| vue网页模板免费| 1p2326| 艾德慕·徒利| 孟州市| 兴和县| hellocarrie88集全自然拼读| 那年那免那些事儿第一季| 欧美激情在线播放| 爱田飞乌番号| 火柴人 电影| 成拼合| 舞蹈生最痛苦的训练方法 | 莱芜香肠哪个牌子正宗| 人鱼的旋律 2003| 相信你还在这里| billbill| 地缚少年君花子君| 开机密码如何更换| 猎人神器外观| 辽宁省| 伤爱罪| 德才鉴定| 性欧美大片| biibii| 健身气功大舞|